Roadwork Continues on State Street Rehabilitation Project from bridge to 1st Ave.
Paving Operations starting 9/29, weather permitting. Dayshift crew working 6 AM – 6 PM, after paving operations Paving operations are weather permitting and will continue from the bridge to 1st Ave. Expect Lane shifts and side street closures to thru traffic. Thru traffic crossing will be located at 1st Ave, 5th Ave, 9th Ave, 15th Ave, 16th Ave, 17th Ave, and State St. Expect loud noises from heavy machinery. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone.
0 Comments
Paving Roadwork Continues on State Street Rehabilitation Project from bridge to 1st Ave.
Nighttime crew working 6 PM – 6 AM, starting 9/17, weather permitting Dayshift crew working 6 PM – 6 AM, after paving operations Paving operations are weather permitting and will continue from the bridge to 1st Ave. Expect Lane shifts and side street closures to thru traffic. Thru traffic crossing will be located at 1st Ave, 5th Ave, 9th Ave, 15th Ave, 16th Ave, 17th Ave, and State St. Expect loud noises from heavy machinery. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Roadwork Continues on State Street Rehabilitation Project from bridge to 1st Ave.
Nighttime crew working 6 PM – 6 AM, no work 9/11 during road relay. Paving will continue from the bridge to 1st Ave. Expect Lane shifts and side street closures to thru traffic. Thru traffic crossing will be located at 1st Ave, 5th Ave, 9th Ave, 15th Ave, 16th Ave, 17th Ave, and State St. Expect loud noises from heavy machinery. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Paving Roadwork resumes State Street Rehabilitation Project from bridge to 1st Ave after Memorial Day Weekend, 9/4 – 9/7
Nighttime crew working 6 PM – 6 AM, 9/8 – 9/10 Paving operations continue from the bridge to 1st Ave. Expect Lane shifts and side street closures to thru traffic. Thru traffic crossing will be located at 1st Ave, 5th Ave, 9th Ave, 15th Ave, 16th Ave, 17th Ave, and State St. Expect loud noises from heavy machinery. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Paving Roadwork continues the State Street Rehabilitation Project from bridge to 1st Ave
Nighttime crew working 6 PM – 6 AM, 8/28 – 9/3 Paving operations continue from the bridge to 1st Ave. Expect Lane shifts and side street closures to thru traffic. Thru traffic crossing will be located at 1st Ave, 5th Ave, 9th Ave, 15th Ave, 16th Ave, 17th Ave, and State St. Expect loud noises from heavy machinery. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Roadwork continues on the State Street Rehabilitation Project in multiple locations
Nighttime work continues next week Nighttime crew working 6 PM – 6 AM Monday thru Sunday Paving resumes 8/25/26. Expect lane shifts and side street closures to thru traffic. Thru traffic crossings will be located at 1stAve, 5th Ave, 9th Ave, and 15th Ave. Paving is expected to be completed prior to Labor Day Holiday. Expect noise and bright light during night work hours. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be open and closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Roadwork continues on the State Street Rehabilitation Project in multiple locations
We will be taking a break from night work starting Sunday August 16th. Day time work hours are from 6 AM to 6 PM. Paving will pause this week once the bottom layer is complete. Thru traffic crossings will be located at 1stAve, 4th Ave, 5th Ave, 9th Ave and 15th Ave. Final paving is expected to be completed by the end of August. Concrete work continues and is expected to be completed by mid-August. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be open and closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Roadwork continues on the State Street Rehabilitation Project in multiple locations
Nighttime crew working 6 PM – 6 AM, Daytime Crew working 6 AM – 6 PM Monday thru Sunday Paving and excavation work continues to move down State Street from 8th Ave to 1st Ave. Expect lane shifts and side street closures to thru traffic. Thru traffic crossings will be located at 1stAve, 5th Ave, 9th Ave, and 15th Ave. Paving is expected to be completed by end of August. Concrete work continues with sidewalks during the daytime from 1st Ave to 17th Ave. Sidewalks are expected to be completed by mid-August. Expect noise and bright light during night work hours. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be open and closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Roadwork continues on the State Street Rehabilitation Project in multiple locations
Nighttime crew working 6 PM – 6 AM, Daytime Crew working 6 AM – 6 PM Monday thru Sunday Starting next week paving removal and excavation work continues to move down State Street from 8th Ave to 1st Ave. Expect lane shifts and side street closures to thru traffic. Thru traffic crossings will be located at 1st Ave, 5th Ave, 9th Ave, and 15th Ave. Concrete work continues with sidewalk during the daytime from 7th Ave to 17th Ave. Expect noise and bright light during night work. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be open/closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. Roadwork continues on the State Street Rehabilitation Project in multiple locations
Nighttime crew working 6 PM – 6 AM, Daytime Crew working 6 AM – 6 PM Monday thru Sunday Milling and paving work continues to move down State Street from 17th Ave to 7th Ave. Expect lane shifts and side street closures to thru traffic. Thru traffic crossings will be located at 7th Ave, 15th Ave, and 17th Ave. Concrete prep continues including curb and gutter work during the daytime from 1st Ave. to the bridge. Expect flagging operations with directions. Expect sidewalk closures and rerouting of pedestrian traffic and access. Expect temporary road closures on side streets as well. Message boards will have more accurate information about what Avenues will be closed each day. Expect delays and stay alert to new traffic patterns during this work. Please follow posted detours or use alternate routes. There will be no on-street parking within the work zone. |